‘Boring’ journey takes HS2 to Little Missenden

by Mark Cantrell
The Little Missenden vent shaft where the two tunnel boring machines reached in August

Two giant tunnelling machines digging HS2’s longest tunnels reached a key milestone in August, after spending two years boring through the earth.

‘Florence’ and ‘Cecilia’ reached the Little Missenden ventilation shaft earlier this month, which puts them more than three quarters of the way through their 10-mile journey beneath the Chilterns.

The enormous 2,000 tonne machines have spent two years excavating the twin tunnels between the M25 and South Heath in Buckinghamshire. They are intended to help improve connections between London, Birmingham and the North of England.

Each machine is a 170-metre long, self-contained underground factory, HS2 explains.

As they dig the tunnel, they have also lined it with 56,000 concrete segments to form rings, and grouting them into place as it moves forward.

They were designed specifically for the geology of the Chilterns. The first tunnel boring machines were launched in Summer 2021 from a site near the M25, and have already excavated approximately two million cubic metres of chalk and flint.

David Emms, HS2’s project client, said: “HS2 will transform rail journeys between London the Midlands and the North, and free up space on the existing network for more freight and local services.

“We’re seeing great progress on the tunnel, which will take our trains deep under the Chiltern hills, safeguard the woodlands and wildlife habits above, and significantly reducing disruption to communities.

“The huge progress that Florence and Cecilia have made would not have been possible without a huge team in support – manufacturing the tunnel segments, excavating the vent shafts – and I’d like to thank everyone involved.”

The excavation of five shafts have been completed. These will provide ventilation and emergency access near Chalfont St Peter, Chalfont St Giles, Amersham and Little Missenden with an intervention shaft at Chesham Road.

The 35-metre deep shaft near Little Missenden – which the tunnelling machines have now reached – is next to the A413 about half a mile from the Buckinghamshire village.

A ‘headhouse’ will be built on top of the shaft to house ventilation and safety equipment, designed to resemble local farm buildings with new planting to help blend it into the surrounding landscape.

The two boring machines are operated by Align, which is a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick.

Each machine has a crew of around 15 people, working in shifts and supported by over 100 people on the surface, who manage the logistics and maintain the smooth progress of the tunnelling operation.

Down to earth

Daniel Altier, Align’s project director, said: “Both [tunnel boring machines] reaching our fourth shaft at Little Missenden is a great achievement for not only the tunnelling team, and the team involved in excavating and preparing the shaft, but also the supporting teams on the surface at the South Portal, manufacturing the concrete segments required to line the tunnel and processing the spoil from the tunnels.

“In particular I would like to pay credit to Align Shafts team, working with our supply chain partners and Keltbray, who have been working over the last few months to ensure the shaft is ready for the arrival of Florence and Cecilia.”

Approximately 2.7m cubic metres of material – mostly chalk and flint – will be excavated during the construction of the tunnels and used for landscaping.

Once construction is complete, the temporary buildings at the south portal will be removed and the site landscaped with around 90 hectares of wildlife-rich chalk grassland habitats.

Chalk grassland used to be widespread across the hills of south east England and are considered habitat of international conservation significance with just 700ha left across the Chilterns.

HS2 currently has five boring machines in the ground, with a further five due to be launched over the coming years. Together they will create 64 miles of tunnel between London and the West Midlands including major tunnels on the approach to London and Birmingham.


Read next: Robot manufacturing makes the most of nature’s bounty

Are you a building professional? Sign up for a FREE MEMBERSHIP to upload news stories, post job vacancies, and connect with colleagues on our secure social feed.

Leave a Comment

Related News

Online building news, features and opinions

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More