Mammoet has installed the first of two 2,200-tonne railway bridges over a Budapest road in a single weekend using self-propelled modular transporters.
The Közvágóhíd railway bridge, built for Hungarian rail and bridge contractor V-HID, crosses Soroksári út, a main route into the city near Budapest Park.
The road was closed from a Friday morning and reopened before the following Monday’s rush hour. The bridge was installed in one piece, which cut the schedule from weeks to days.
The structure is part of the Ferencváros – Kelenföld railway line capacity expansion project. V-HID approached Mammoet in March 2025.
Two bridges will be installed, north and south, each measuring 108 metres long and 20 metres wide. The south bridge went first, with the north bridge due about a year later.
V-HID has previously launched bridges by skidding them over temporary support towers. That method would have required 20-metre piles to be drilled into the road, closing it for an extended period to allow access for drilling machines.
Mammoet instead proposed assembling support masts on top of the transporters and driving them under the bridge. The masts could be removed after use, avoiding repairs to the road surface.
The bridge sections were delivered by truck, then assembled, coated and welded on site. Space was the main constraint, with three separate areas needed to receive and assemble the bridge sections, transporters and masts. An old tram station was removed to make room for the mast assembly area.
Four sets of transporters worked at two levels to launch the bridge and support its weight. The bridge was driven forward until it was cantilevered, and the first set of transporters then drove beneath it with its masts.
Each mast was made from sections of an MSG crane mast on a base frame, with four masts per transporter set and load spreaders underneath.
As the bridge moved forward, further transporter sets were lowered in single lines from the upper to the ground level using a 400-tonne mobile crane. The sets were then reconfigured, collected masts from the assembly area and drove under the bridge.
Three sets of transporters, each made up of four 12-axle lines, were under the bridge when it reached both abutments. The operation used 176 axle lines in total.
The north bridge will be installed in the same way, but with less space available because of the south bridge.
Mammoet project manager Jordy van der Hoeven said: “Our expertise and flexibility in terms of engineering solutions and equipment, allows us to adapt to technical challenges.
“We always find a way because if we don’t have something in our fleet to fix or solve a problem, we build it.”